Data Center Watch
Data Center WatchMarketsUnited States › Project Tango

Project Tango

us tracker · approved/permitted/under construction — Loxahatchee, FL, United States

3,700,000Sq ft
Find on the live globe →OpenStreetMap ↗Primary source ↗
Status
approved/permitted/under construction
Type
us tracker
Location
Loxahatchee, FL, United States
Address
near 20125 Southern Blvd
Power source
Grid (unspecified mix)
Cooling
Closed loop
Purpose
data center / colocation (ATLAS directory)
Coordinates
26.6948, -80.3718 (city-level)
As of
06/08/2026
Palm Beach County zoning commission recommended approval of the plans in December 2025. Plans include a dedicated substation. At full build-out, estimated water use is about 5,000 gallons per day. Power will be provided by Florida Power & …

Source: FracTracker Alliance National Data Centers Tracker