Skybox Austin Data Center Campus
Skybox Datacenters · us tracker · approved/permitted/under construction — Pflugerville, TX, United States
30 MWGross power
289,740Sq ft
- Operator
- Skybox Datacenters
- Owner
- Skybox Datacenters
- Status
- approved/permitted/under construction
- Type
- us tracker
- Location
- Pflugerville, TX, United States
- Address
- 600 New Meister Ln / 2515 S Kenney Fort Blvd
- Coordinates
- 30.4824, -97.6246 (city-level)
- As of
- 07/13/2026
Mast-planned 25-acre campus, two buildings. Building/Austin 1 (600 New Meister Ln): 141,240 SF, 30MW, completed 2023. Building/Austin 2 (2515 S Kenney Fort Blvd): 148,500 SF, expected completion 2025.
Source: FracTracker Alliance National Data Centers Tracker