23 tracked data centers from 16 operators, 11,027 MW disclosed.
| Facility | Operator | Status | Power |
|---|---|---|---|
| New Era Energy & Digital Data Center | — | proposed | 7,000 MW |
| Green Data Center | — | cancelled | 2,000 MW |
| Zenith Volts Data Center | — | proposed | 1,240 MW |
| Project Jupiter | Open AI/Oracle | approved/permitted/under construction | 700 MW |
| Meta Los Lunas | Meta | ai_campus | 87 MW |
| H5 Data Centers Albuquerque | H5 Data Centers | operating | — |
| bigbyte.cc | bigbyte.cc Corp | operating | — |
| Oso Grande Technologies | Oso Grande Technologies, Inc. | operating | — |
| Centersquare Albuquerque (ABQ1) | Centersquare | operating | — |
| 400 Tijeras Ave NW | Cyxtera | listed | — |
| 505 Marquette -- Lobo Internet | Lobo Internet Services, Ltd | operating | — |
| Aerospace Data Facility Southwest | — | operating | — |
| Albuquerque | NOVA Corporation | listed | — |
| Centersquare ABQ1 | Centersquare (formerly Evoque) | listed | — |
| Centersquare Albuquerque Data Center | — | operating | — |
| Hobbs Data Center | — | operating | — |
| Los Lunas Data Center | Meta | listed | — |
| New Era Lea Data Center | New Era Energy | listed | — |
| PRISM Technologies | PRISM Technologies | listed | — |
| ServerCondo-219 Albuquerque | IXNM, INC. | operating | — |
| Southwest Cyberport Albuquerque | Southwest Cyberport, Inc. | operating | — |
| Stargate - Project Jupiter | Stack Infrastructure | listed | — |
| Zenith Volts Roswell Data Center | Zenith Volts | listed | — |